Read first
The unit is rented and the demand is not there
A founder with a good-selling product signs a lease for a shed, orders a mixer and a filling machine, and hires two people. Six weeks later orders dip after a festival and the fixed costs do not. The unit was not the mistake. The order was: she built the factory before she knew what a steady month looked like.
This page is the sequence for a brand that has decided to make its own product. If you have not decided, start with should my brand make its own product or use a contract maker, which sets out the signs and the cost check. The licences are in licences for a brand that makes its own product.
The order of work
- Prove demand with a maker first. A few months of steady orders from a contract batch show the volume your unit has to serve. See first batch size.
- Choose the premises with the rules in hand. A residential flat may not be allowed to run a unit; see commercial use and zoning. Ask the licensing authority what it needs to see about the building, water, power and layout before you sign a lease.
- Register the business and the unit. Udyam registration is free and online; see Udyam registration. GST registration in the unit's State; see GST for online goods sellers.
- Apply for the category licence in your own name, and plan for the wait before you buy machines. Cosmetics are decided within 45 days if requirements are met, per the licences page; other categories have their own times.
- Get written quotes for every machine, at least three each, with installation, power needs, warranty and spares. We found no sourced capex range for a small unit, so do not copy a figure from a blog.
- Line up raw material suppliers with their own licences and test reports, and ask about minimum quantities and payment terms. Raw material and packaging stock is cash.
- Write the batch record and quality checks before the first batch; see quality control per batch.
- Hire for the first month only, and track the headcounts where PF and ESI begin: EPF at 20 employees; ESI at 10 persons. See PF and ESI for a small team.
What a unit changes compared with a contract maker
| Question | Contract maker | Your own unit |
|---|---|---|
| Whose licence | The maker's (plus a loan licence for some categories) | Yours, with an inspection of your premises |
| Cash tied up | A batch and an advance; see advance to a maker | Machines, deposits, raw material, packaging and wages before the first sale |
| Fixed cost | Almost none | Rent, power, wages and licences every month, sold or not |
| Margin | The maker's margin is in your price | You keep it, once volume covers the fixed cost; see the cost check |
| Speed of change | Waiting for the maker's slot | Change a batch yourself |
| Risk of a bad batch | Shared by contract; see bad batch already sold | All yours, and so is the recall |
| Your time | Orders, calls, checks | Production, staff, compliance and quality as well as the brand |
The money, without an invented number
Work out your own unit cost in four lines. Monthly fixed cost (rent, power, wages, licences, loan instalments). Cost of materials and packaging per unit. Units you can sell in a bad month, not a good one. Your price less the platform and shipping costs of selling it. If the fixed cost divided by the units gives a number higher than the margin a contract maker's price would have given you, the unit is not ready; see landed cost and contribution margin.
Funding the machines is a separate question from funding the stock. Loans and schemes for small units exist, and are covered in loans and schemes for a D2C brand and brand schemes and loans. Check each scheme's current rules before you plan around it.
If you are small, or already bigger
A starter brand that makes in a rented kitchen or a small shed can keep a contract maker for the lines it cannot yet make and bring in one line at a time. A brand past a few hundred orders a month has the data for a real cost check, and should run a month of the numbers above before it signs a lease. A brand with seasonal sales should plan for the low month, since the unit's cost does not fall with demand. Many brands keep a maker as a second source even after the unit opens, so that one machine breaking does not stop sales.
What usually goes wrong
- Leasing premises that the licensing authority later rejects.
- Buying machines before the licence is granted.
- Sizing the unit for the busiest month.
- No written batch record, so a complaint cannot be traced to a batch.
- Hiring staff before the first batch and carrying wages through a quiet month.
- Closing the contract maker relationship at once, and having no second source.
This page is general information, not legal or financial advice. We found no sourced capex figures for a small unit; use quotes. Check pollution and factory approvals with your State authority, since we did not research them.
Plan your unit
If you want to test your numbers before you sign a lease, tell us where you are.
Questions people ask
How much does a small unit cost?
We found no sourced figure. Get three written quotes per machine and add premises, licences and a month of wages and materials.
Do I need a licence before I buy machines?
Plan for the licence first; the wait can be weeks. For cosmetics, the Cosmetics Rules allow 45 days to decide if requirements are met.
Should I stop using my contract maker once the unit is ready?
Many brands keep one as a second source. A single unit is a single point of failure.
Where these numbers come from
- Staff counts at which EPF and ESI start: EPF at 20 employees; ESI at 10 persons (India; Code on Social Security; basics.epf-employee-threshold and basics.esi-employee-threshold hold the wage ceilings). Official source: India Code (checked research 2026-11-14), checked 13 November 2026.
Fees, rates and rents change. Check the official source before you pay or sign anything.
What now?
Where are you?
One tap, and we point you to the right next step.