Why do fit-out budgets run over?
The contractor quotes ₹36 lakh at a neat rate per square foot. By the third month there is a bill for the hood, the electrical upgrade, the bar counter and the loose furniture, none of which were in the quote. First-time owners often budget only the interior, which is roughly half the project. Interior fit-out is about 35–50% of project cost; the kitchen and back-of-house are another 35–45%, and mechanical, electrical and plumbing work takes 25–35%.
What does a quote cost, and what is in it?
Quotes disagree because scope disagrees. Chennai firms quote casual dining interiors lower than Delhi NCR ones, partly city and partly what is included. The reference range for casual dining is ₹1,000–4,500 per sq ft, and by quality 900-1,400 / 1,400-2,200 / 2,200-3,500+ for basic, mid and premium, excluding GST and kitchen equipment. Small units cost more per square foot.
Ask each contractor to price the same list, line by line:
A reported example is a '₹36 lakh quote at ₹1,800 a square foot' that leaves out three of the above: smaller, not cheaper. Work out the total project from the cost to open a restaurant before you compare it with a quote.
How do I choose the contractor?
- Visit finished restaurants the contractor built, ideally two years old, and ask the owners about delays and after-service.
- Ask who does the kitchen. Many interior firms subcontract the kitchen and exhaust. Make sure the same party is responsible for the whole system.
- Check the drawings. A good contractor produces layout, electrical, plumbing and exhaust drawings that match your kitchen layout, not a render.
- Ask about fire and licence drawings. Whether they prepare what the fire authority needs and who submits it.
- Check the team. Who is on site every day, and how many projects the firm runs at once.
- Look at the references and the paperwork. A GST registration, a written contract and a named person who answers the phone.
How do I protect the budget?
- Fix the scope in writing with drawings, a bill of quantities and brand and spec for the main items.
- Pay in stages tied to work completed and checked, with a final amount held until the handover and snag list are done.
- Get changes in writing. Every variation gets a written price before work starts.
- Keep contingency. Hold 8–12% for what you did not see, and do not spend it on design upgrades.
- Get the rent-free period right. Ask the landlord for the longer end of 1–3 months so the build does not run on rent. See lease terms.
- Sequence the licences. Start the fire and other applications while building, so the opening date is not held by paperwork.
- Visit the site weekly with a checklist, and photograph progress.
Never pay the whole kitchen cost to the interior contractor before the equipment is ordered and delivered. Pay the equipment dealer directly where you can, against an invoice.
How long does a fit-out take?
The checked research did not source a reliable build time for restaurants, so treat any time a contractor gives as a promise to test. A plan from one source puts opening four to seven months after the site hunt starts, with fit-out in the middle. Ask each contractor for a week-by-week programme, and ask what happens if a licence is late. Rent keeps running either way.
What usually goes wrong
- Comparing quotes with different scopes.
- No loose furniture, bar or signage in the base quote.
- Paying 70% up front and then running out of leverage.
- A contractor who subcontracts the exhaust to a cheaper firm.
- Changes agreed on WhatsApp and disputed at the end.
- Starting before the exhaust route and fire plan are approved, then redoing work.
- Spending the contingency on nicer lights.
Apply it to your own case
Write the scope list above for your restaurant, send it to three contractors and ask each to fill it line by line. Add the kitchen quote and the equipment separately and compare totals. Tell us your city, size and type and we can say what owners there usually find missing from the quote.
Questions people ask
How much does a restaurant fit-out cost per square foot?
Casual dining interiors are reported at ₹1,000–4,500 per sq ft; by quality 900-1,400 / 1,400-2,200 / 2,200-3,500+. City, scope and size change it a lot.
How much contingency should I keep?
About 8–12%.
What do fit-out quotes usually leave out?
Loose furniture, decorative lights, the bar counter, kitchen drains, wiring to equipment, air-conditioning, power upgrade, signage, POS and CCTV, licences and professional fees.
How should I pay a contractor?
In stages tied to work completed, with a final amount held until handover and snag list are done.
Where these numbers come from
- Contingency to keep in a restaurant project budget: 8–12% (Gurgaon contractor). Reported: Brandroot Interiors, restaurant interior design in Gurgaon, checked 14 November 2026.
- Interior fit-out per sq ft, casual dining, by city: ₹1,000–4,500 per sq ft (Chennai 1,000-1,800; Delhi NCR 2,500-4,500 (Gurgaon 2,500-4,000); Bengaluru all-in 3,500-5,500; ex-kitchen equipment, and the city and the scope of each quote differ). Reported: Asaya Interiors, restaurant and cafe interior cost (Delhi NCR), checked 14 November 2026.
- Interior fit-out per sq ft carpet, basic / mid / premium: 900-1,400 / 1,400-2,200 / 2,200-3,500+ (India metro and tier 2, excluding GST and kitchen equipment). Reported: Aaditya Interior, restaurant interior cost per sq ft (14 October 2026), checked 14 November 2026.
- Typical rent-free period for fitting out a shop: 1–3 months (metro and tier 2 cities; negotiated, not a right). Ballpark Commercial leasing guides (2026) give 1–3 months rent-free for retail and food tenants (30–90 days in a retail leasing guide), longer for bare-shell spaces. Small landlords on 11-month agreements often give two to four weeks or none.
Fees, rates and rents change. Check the official source before you pay or sign anything.
Place and setup · Restaurant
More on place and setup for a restaurant
14 pages on this. You are on number 11.
- How big should my restaurant be, and how many seats do I need?
- What fire safety, grease trap and gas safety does a restaurant kitchen need?
- How do I design a restaurant dining room and seating on a budget?
- How much rent can a restaurant afford for its expected sales?
- How do I hire a restaurant fit-out contractor and stop the budget running over?
- What should a property have to work as a restaurant: exhaust, water, drainage, power, gas and washrooms?
- What should a restaurant negotiate in its lease: rent-free period, lock-in, escalation and renewal?
- What must my landlord allow for a restaurant: cooking, exhaust, signage and outdoor seating?
Reading about it is one thing; doing it in your restaurant is another. If you'd like a hand choosing and setting up the right place, tell us where you are and a person will reply, free.
Get help with this ↓What now?
Where are you?
One tap, and we point you to the right next step.
What to read next
Related questions
Where this fits in your journey
- Step 7 of 8How to open a second restaurant without breaking the first: Pick the place, then fit out and license it→
- Step 8 of 15How to open a restaurant in India, step by step: Plan the kitchen and fit-out, and hire a contractor→
- Step 8 of 8Taking over the family restaurant: where to start: Refresh the room, and decide whether the name stays→