Buy the items that are used on every site and wear out slowly: steel or ply shuttering and props, scaffolding, a concrete mixer, needle vibrators, a water pump, levelling instruments, site tools and basic safety gear. Hire everything heavy and occasional, such as excavators, transit mixers, cranes and hoists, by the hour or day.
As a ballpark, a residential contractor can equip two or three house sites for roughly ₹10–25 lakh in owned equipment, with working capital on top. The common mistake is buying a JCB or a tower crane because the work might come. A machine that sits idle through monsoon still carries EMI, insurance and an operator you must pay.
Shuttering and scaffolding: the stock that decides your margin
Formwork is the largest owned asset for a building contractor, and the one that quietly earns or loses money. Every slab, beam and column needs it, and how many times you can reuse it before it is scrap sets your cost per square foot of slab.
| Item | Estimated cost | Buy or hire, and why |
|---|---|---|
| Adjustable steel props (telescopic) for slab support | ₹400–900 each, new | Buy. A single ground-plus-one house can need hundreds; buy enough for one slab and re-use it on the next pour |
| Steel centring plates or ply-and-frame panels | ₹150–300 per sq ft of panel | Buy for repeat sizes. Timber and plywood shuttering is cheaper on day one but does not last |
| Cuplock or frame scaffolding sets | ₹3,000–5,000 per frame or per tonne-based sets, varies widely | Hire per day per frame for the first jobs, buy once you are always short |
| Bamboo or casuarina poles and ropes | Small | Still used for light work in many towns; confirm what your site engineer and clients accept |
| Steel bar bending table, cutter and bender | ₹20,000–1.2 lakh | Buy. Bar bending can be hand-powered or a motorised bender, depending on volume |
| Column boxes and beam sides | Included in your panel stock | Buy to your most common column and beam sizes |
Count your reuse. If a ply sheet or a set of panels is good for a fixed number of pours, its cost per pour is the price divided by that number. A cheap material that lasts three pours often costs more per slab than a dearer one that lasts thirty. Keep a simple tally of pours per set so you know when to scrap.
How much formwork a slab, beam or column needs, how long it stays in place, and how it must be propped are decisions for the structural engineer and the site engineer on the job. This page only covers what to buy, not how to build safely.
Small machinery to own
The machines worth owning are small, rugged, and used almost daily. They also have local repair mechanics who can fix them in a day.
| Machine | Estimated cost | Note |
|---|---|---|
| Concrete mixer (half-bag or one-bag, with hopper) | ₹60,000–2 lakh | The workhorse of house sites where ready-mix is not practical. Hopper type needs less labour than drum-feed |
| Needle (poker) vibrators with motor | ₹15,000–60,000 | Buy two per site-set so a failure does not stop a pour |
| Water pump (monoblock or submersible) | ₹6,000–30,000 | Needed for curing, basements, and pumping out monsoon water in pits |
| Plate compactor or rammer | ₹40,000–1.5 lakh | For backfill and plinth beds; the model you rent now may suit you to buy later |
| Cut-off saw, angle grinders, chasing cutters | ₹3,000–25,000 each | Cheap to own, but hire out labour carefully: tools go missing |
| Material hoist (small builder's winch or gantry) | ₹60,000–2.5 lakh | Hire first. Check the supplier's operator and safety setup yourself |
| Generator set for sites with poor power | ₹60,000–2 lakh | Fuel is the real cost; keep a running log per site |
Levelling, measuring and testing kit
Small instruments protect you from disputes and rework. Cheap kit used daily is worth more than a big instrument in a cupboard.
- Auto level or dumpy level with staff and tripod (about ₹15,000–45,000). Used by the site engineer for plinth and slab levels. A total station is a later purchase, or hire a surveyor.
- Laser line or rotary level (about ₹6,000–40,000) for tiles, false ceilings and finishing checks.
- Measuring tapes (30 and 50 m), plumb bobs, spirit levels and string lines (a few thousand rupees in all) for every gang.
- Cube moulds for concrete cube samples (about ₹800–2,000 each). Testing the cubes is done at a lab; ask the engineer on your project how many and when, and keep the reports.
- A good camera phone with a tripod and a site-board for dated progress photos, which settle more bill disputes than any argument.
Keep a calibration and handover note for instruments. Clients and architects do check that your level is not a decade old and out of true.
Site office, store and safety on a small site
A site is a mini-workplace. Without a lockable store, cement gets rained on and tools walk away. Without basic safety, one injury can stop work, bring in the labour department and cost far more than the gear.
| Item | Estimated cost | Why |
|---|---|---|
| Portable cabin or tin-shed store and site office | ₹60,000–2.5 lakh | Lockable store for cement, binding wire and tools; a desk for the engineer and records |
| Cement shed with raised platform | ₹15,000–60,000 | Keeps bags off the ground and out of damp. Cement stored badly loses strength |
| Helmets, safety shoes, gloves, reflective vests | ₹1,000–2,500 per worker | Issue and record; make the habit visible from day one |
| Safety harnesses and lifelines for work at height | ₹1,500–6,000 each | Check that the anchorage and use are right with a competent safety person |
| Barricades, warning tape, edge protection and signs | ₹15,000–60,000 per site | Keep trenches, shafts and slab edges guarded |
| First-aid box and a tie-up with a nearby clinic | ₹3,000–8,000 | Know the nearest hospital and keep contacts on a board |
| Temporary electrical board with earth-leakage protection | ₹8,000–35,000 | Have a qualified electrician install and inspect it |
| Drinking water, toilets and a shaded rest area for labour | ₹10,000–50,000 | Required in spirit and often in law for sites above a size; confirm what applies |
Safety duties on construction sites, including welfare facilities, safety officers and training, come from labour law, which has recently moved into new codes with state rules still being notified. We have not verified the current specifics for your state. Confirm with a labour consultant and the state labour department. This is not legal advice or a safety plan.
What to hire instead of buying
Rental is how small contractors take on work they could not afford to equip for. The rule is to buy what you will use on most working days, and hire the rest.
| Hire this | How it is usually charged | What to check |
|---|---|---|
| Excavator or backhoe loader (JCB) | Per hour or per shift; fuel and operator usually extra or included, so ask | Who pays idle hours when it rains; whether travel to site is billed |
| Transit mixer and concrete pump | Per cubic metre of ready-mix, pump per hour or per cubic metre | Minimum quantity, waiting charges and who arranges access for the truck |
| Tower crane or mobile crane | Per day or per month, with operator and a certified rigger | Their licences and inspection records. Lifting is not a place to economise |
| Tippers and tractor-trolleys for sand, aggregate and soil | Per trip or per load | Weighbridge slips or load counts; local mining and transport rules |
| Scaffolding for a short project | Per frame per day | Count on delivery and return; damaged frames are billed |
| Dewatering pumps and generators for a peak | Per day | Fuel responsibility |
For ready-mix, a plant check matters more than the price. Ask the plant which mix designs they supply, their cube test results and how they handle delays; see finding suppliers.
What not to buy yet
- A JCB, a transit mixer or a crane before you have steady work booked. Hire until your hire bill for the same machine is higher than a year of EMI plus operator plus servicing.
- A big vehicle fleet. A pickup or a small goods carrier for materials and a motorbike for the supervisor go a long way.
- A large head office. A small rented office near the main sites, with a plan table and a meeting corner, is enough. Spend on a site cabin instead.
- Heavy, rare formwork for a building type you have not yet built. Rent or buy used when a job demands it.
- Expensive ERP or tender software before you have lived with a good spreadsheet for a season. See the software page.
- Land or stock for speculation. Developing flats is another business, with a promoter's duties and RERA. Learn it separately; see the full playbook.
Insure what you own and what you build: contractor's all-risk cover for the works, workmen's compensation or a suitable employee cover, and machinery cover. Ask an insurance broker which policies suit your contracts; policy wording differs, so read exclusions.
Paying for it
More on starting a construction company
- Start hereThe full playbook →Models, licences, startup costs and the steps to your first customer.
- Go deeperWho to hire →Site engineer, supervisor, labour gangs and accounts: hiring order, pay and how to vet each.
- Go deeperGetting customers →Architects, plot owners and tenders: how a small contractor wins its first ten jobs.
- Go deeperFinding suppliers →Cement, steel, sand, RMC and hire machinery: where to source, how to vet, credit terms and red flags.
Questions people ask
How much equipment does a small building contractor need?
A small contractor running two or three house sites typically owns shuttering and props, scaffolding, one or two concrete mixers, needle vibrators, a pump, levels and safety gear, which might total roughly ₹10–25 lakh. Heavy machines like excavators, transit mixers and cranes are hired. Treat these as estimates and price your own mix locally.
Should I buy a JCB or hire one?
Hire until your own work makes it busy most days. A machine carries EMI, an operator, fuel, servicing and idle days in the monsoon. Compare a year of hire bills against the full yearly cost of ownership, and buy only if the work is already booked. Many small contractors never buy one.
Is it cheaper to buy used shuttering and scaffolding?
Often yes, because steel props and panels last many pours, and used sets are sold when other contractors close projects. Inspect for bends, cracks, weld failures and rust, and insist on counting items at delivery. Whatever you buy, the engineer on your project decides how it is used, not the seller.
Do I need to buy testing equipment for concrete and steel?
Usually only cube moulds and basic site tools. Strength tests for cubes, steel and other materials are done in a testing lab that gives a report. Ask your project engineer what testing the specifications call for, keep every report with your records, and do not rely on your own readings for safety decisions.
What insurance should a contractor buy at the start?
Commonly a contractor's all-risk policy for the works, a workmen's compensation or employee policy for site labour, and cover for machinery and vehicles. Contracts often specify insurance, so read them first. Ask an insurance broker for current options and exclusions; premiums depend on the project value and risk.