A charging station depends on five suppliers: a charger maker, an electrical contractor, the DISCOM that gives you power, a charge-point management platform, and a landlord. The weakest one decides your uptime, so vet all five before you sign with the first.
The mistake most people make is picking the cheapest charger and the nearest electrician. A cheap charger with no local service team is a stranded asset, and a contractor who has never done an HT or DC install can leave you with failed inspections. This page sets out where to find each supplier and what to ask.
The five suppliers and what each one controls
| Supplier | Controls | Where to find them |
|---|---|---|
| Charger manufacturer or importer | Hardware quality, firmware, spares, warranty | Trade fairs such as EV and renewable-energy expos, charging-industry directories, existing stations' nameplates |
| EPC or electrical contractor | Panel, cabling, earthing, commissioning, inspection papers | DISCOM-empanelled contractors, charger OEM channel partners, solar EPC firms |
| DISCOM | Connection, meter, tariff category, load | Online EV or new-connection portal of the state DISCOM |
| Charge-point management software | Billing, monitoring, roaming, reports | Charger OEMs, independent platform vendors, public-sector aggregators |
| Landlord or site host | The location, the bays, the lease | Property brokers, existing relationships, public-land owners |
Under the national guidelines the DISCOM must provide connections within set timelines, usually between three days in metros and 90 days where the network must be extended, and should run an online single-window portal for charging-station applications. In practice these timelines vary by state, so ask what the local one is.
Choosing a charger maker
Charger brands in India range from long-standing electrical-equipment makers and international importers to start-ups that assemble units locally. The datasheet matters less than the service behind it.
- Certification: ask for the BIS test report and the standard it was tested to, plus the OCPP conformance statement. Do not accept a verbal assurance.
- Service footprint: where is the nearest field engineer, what is the guaranteed response time, and are spares such as contactors, cooling fans, cables and gun heads stocked in India?
- Warranty terms: what is covered (module, cable, enclosure), what voids it (monsoon water entry, surge), and who pays for the visit?
- Firmware access: can your CMS vendor connect via OCPP, and does the maker charge a fee for configuration changes?
- Reference sites: ask for three live sites at least a year old, and call the owners to ask about uptime.
- Modular design: a DC unit built from power modules lets you replace one module without taking the whole charger offline.
Also ask about the ruggedness of the enclosure. Dust, heat and salt air near the coast shorten the life of cheap enclosures, and a unit rated for the temperature at your site matters more than extra kW.
Electrical contractors and the inspection trail
The contractor decides whether your site passes the electrical inspection and whether it still works after the first monsoon. Hire for charging-specific experience, not just general wiring.
- Ask for past EV or solar commissioning work and the inspection certificates, not just photos.
- Check licensing: the work should be carried out by a contractor with a licence recognised by your state's electrical inspectorate. Ask what they do for the inspection of larger installations.
- Get a line-item quote covering panel, cable, trenching, earthing, meter box, and testing, so you can compare bids and spot padding.
- Insist on the single-line diagram, earth-pit readings and the commissioning report as handover documents.
- Define who fixes snags during the first 12 months, and who is on the phone at 9 pm if the incomer trips.
Safety and inspection requirements for charging stations come from CEA regulations and state inspectorate practice. We have not listed section numbers or thresholds; confirm what applies to your load with the state electrical inspectorate. This is not legal advice.
Terms, credit and who carries the risk
| Term | What to try for | Red flag |
|---|---|---|
| Charger payment | 30 to 40 percent advance, balance on commissioning, retention until uptime is proven | 100 percent advance on a factory in another state |
| Warranty | At least a year on the charger and a longer term on power modules | Warranty void if any non-vendor electrician touches the panel |
| AMC (annual maintenance contract) | Fixed response time, a spare kit on site or nearby, uptime commitment | No response commitment and unlimited exclusions |
| Software | Monthly per-charger fee or a small share, with data export on exit | Lock-in with no way to move chargers to another platform |
| Lease | Long enough to recover capex, with a clear renewal and exit clause on chargers and meters | Short lease with a rent review tied to your sessions |
| Revenue share | Share on kWh sold with an audit right | Share on gross revenue with no access to your session data |
Backups, spares and red flags
- Keep a starter spare kit for the single most failure-prone parts: a charging cable and gun, a contactor, an extra fan or filter, and a key set for the enclosure.
- Have a second electrician on your phone list, in case your main contractor is unavailable.
- Hold two charger brands across a multi-site network if you can, so one bad firmware release does not take down the whole network.
- Red flags: claims of guaranteed income per charger, no BIS paperwork, refusal to show reference sites, a platform that will not export your session data, and pressure to sign before the DISCOM has confirmed the load.
- Be wary of turnkey franchise offers that promise returns; ask for the actual utilisation figures of live sites before you sign.
Once suppliers are shortlisted, align them with your software choice and the budget in what to buy. If you are also thinking of solar to cut daytime power costs, our solar installation business page covers who installs and what to ask.
More on starting a EV charging station
- Start hereThe full playbook →Models, licences, startup costs and the steps to your first customer.
- Go deeperWhat to buy →AC and DC chargers, panel and cabling, metering and safety kit, costed, with what to delay.
- Go deeperGetting customers →Fleets, map listings, roaming and host partners, plus launch pricing and idle fees.
Questions people ask
Where do I buy chargers for a public charging station in India?
Buy from an established charger maker or importer with a service team in India. Find them through EV and renewable-energy expos, existing stations' nameplates and industry directories. Ask for BIS test reports, an OCPP statement, three reference sites and the response time for a field engineer before you compare prices.
Who installs the charger and does the wiring?
A licensed electrical contractor, often the charger maker's channel partner or a solar EPC firm, does the panel, cabling, earthing and commissioning. Ask for a line-item quote, past commissioning certificates and the handover documents. Larger installations may need an inspection by the state electrical inspectorate before they are energised.
How long does the DISCOM take to give a connection?
The national guidelines refer to timelines of about three days in metros, seven in other municipal areas, 15 in rural areas and up to 90 days if the network needs extending. These come from the Electricity (Rights of Consumers) Rules as amended. Real timelines vary by state and by feeder, so confirm locally.
What should an annual maintenance contract for chargers include?
It should include a guaranteed response time, scheduled preventive visits, the parts covered, who supplies spares and a commitment on uptime. Ask what is excluded, such as water damage, vandalism and surge. Avoid contracts with unlimited exclusions or no stated response commitment.
Should I rely on a single charger brand?
For one site, a single brand with good local service is fine. As you grow, consider a second supplier, so that a bad firmware release or a supply delay does not stop your whole network. Whatever you choose, insist on OCPP so that chargers can be moved to another software platform.